A retaining wall that sits on the line between 2 Calgary lots will get measured by 3 different people over its life, the planner, the building inspector, and the land surveyor who draws the real property report when one of the 2 houses is sold, and each of them has been handed a different tape. Most of the trouble we have read about on these walls starts there, with a homeowner who built to 1 ruler and then got measured with another, and the frost and the neighbour only arrive after that.
The City Has 2 Rulers, 1 Metre And 1.2 Metres

The number everyone in Calgary remembers is 1.2 metres, 4 feet, because that is the one on the City’s fences and retaining walls page, a permit is typically required when a wall retains 1.2 metres or more of soil. What fewer people have read is the permit checklist for retaining walls, which has a second number in it, and the second number comes first. An approved development permit is required if the wall is 1 metre or higher at any point, and the building permit, with structural plans stamped by a practising Alberta engineer, kicks in once the wall exceeds 1.2 metres. So a wall built to 1.1 metres has cleared the famous 4 foot line and has still crossed the planner’s.
- A development permit at 1 metre and a building permit at 1.2 metres are 2 separate applications, and only the second one needs an engineer’s stamp.
There is a third line on that checklist which most contractors will not mention in a quote, and it is that a Safety Codes Officer may require a building permit and an engineer’s stamp for a wall under 1.2 metres if the project is complicated enough, so a short wall holding up a driveway or sitting over a gas line could be pulled into the engineered category by the inspector on the day.
Does a garden box count towards any of this? It does, the City adds up every retaining wall and garden box within 1 metre of each other and treats the total as 1 wall, which is why the 3 small tiers on the right of the drawing above are being measured with 1 line. Three tiers of 500 mm with a metre between them would have been 3 walls, the same tiers built 600 mm apart are a 1.5 metre wall with 2 permits attached.
A Fence On Top Is Measured As Part Of The Wall
Most lot line walls in this city end up with a fence on them within a year, because the reason the wall is on the line at all is that the 2 yards sit at different heights and somebody wants privacy over the top. The City’s page on this is 1 sentence long and it settles the argument before it starts:
Retaining wall and fence heights are measured from grade to the top of the fence.
A rear fence needs a permit above 2 metres, a front yard fence above 1.2 metres, and those limits are read from the ground on the low side to the top board, with the wall underneath counted in. I paid for a 1 metre wall and the City is telling me I have a 2.8 metre fence? That is how it will read on the inspector’s sheet if a 1.8 metre privacy fence has been bolted onto the cap, and Sungreen, who have been building these in Calgary since 1990, add the part the City does not, which is that a solid 6 foot fence on top of a wall is a wind sail the wall was never designed to carry, whereas an open picket or a metal rail hardly loads it at all. Their rule is to keep the posts off the cap altogether and set them in their own holes behind the wall, so the fence and the wall stay 2 structures even when they look like 1.
The 4 Foot Frost Line Is A House Rule, Not A Block Wall Rule

Calgary asks for 1.2 metres of ground cover over a house footing for frost protection, and we had started this piece believing that number applied to every wall in the yard as well. It took the block maker’s own embedment page to correct us. Allan Block, whose segmental block is what most Calgary landscapers lay, buries a minimum of 150 mm of block, sets it on 100 mm of compacted gravel for a wall under 1.2 metres and 150 mm over that, and says plainly that in most cases the embedment does not need to go below frost depth, because the gravel pad is what takes the freeze and thaw movement. Sungreen’s own number for a wall around 1 metre is a base 300 to 500 mm below grade, and they only go down to the frost line on taller or heavier walls where the load justifies the digging.
- A dry stacked block wall is built to move a little on its gravel pad every winter and settle back, a mortared or poured wall on a footing is not, and that second kind is the one in the picture.
The brick wall on the left of the drawing is sitting on a concrete footing that stops above the frost, so when the water in the soil freezes and expands it has nowhere to push but up, and it pushes the footing with it, and it does this unevenly because the soil under 1 end of the wall holds more water than the other, which is where the crack comes from. This concern was even written into a poem, Robert Frost’s Mending Wall, where 2 neighbours walk their boundary wall every spring putting back the stones that the frozen ground has heaved out over the winter, and the line everybody quotes from it, good fences make good neighbours, is said by the neighbour, not by Frost, who spends the poem wondering why they bother. If the wall on your line is mortared stone or poured concrete, the footing goes below the frost, which in this city means digging to 1.2 metres. If it is block, you would be paying for a 4 foot hole the block was never going to use.
Where The Water Goes Behind The Wall

The cutaway above is the part of the wall you will never see again once the sod is back, which is why it is the part to ask about before the sod goes down. Behind the block sits a column of clean drain rock, a perforated pipe lying at the base of it, filter fabric between the rock and the native soil so the clay cannot silt the rock up, and an outlet that lets the pipe empty somewhere lower than the wall. On a block wall the makers vent that pipe to daylight about every 50 feet, the weep holes every few feet in the drawing belong to a solid poured or mortared face where the water has no other way through.
Parts of Calgary sit on clay, and clay holds the spring melt against the back of a wall for weeks instead of letting it through, so a wall on a clay lot without the rock and the pipe will have been carrying wet soil through April and then carrying frozen wet soil through the next winter. The pipe needs somewhere to go, and on a lot line wall that somewhere is sometimes the neighbour’s yard.
Whose Wall It Is When It Sits On The Line

When either house is sold, an Alberta land surveyor will draw a real property report, and the City’s list of what that report has to show reads houses, decks, sheds, fences, retaining walls, window wells and air conditioning units, so the wall will be on the drawing whether anyone remembers who built it. The certificate of compliance that the buyer’s lawyer then asks the City for costs $189 and comes back in a day or 2, and this is the part that surprised us:
- The certificate of compliance does not check a retaining wall or a fence against the bylaw at all, the City says a site plan cannot show whether they comply, it only checks whether the wall has crossed onto City land.
So a wall that was built without its permit will sail through compliance, and a wall that is 200 mm over the line into a City lane will not, and the second one is the expensive one, because an encroachment on City land either gets an encroachment agreement signed or it gets removed, and the fine for leaving it there runs from $750 to $10,000 on conviction. The permit history is a separate search on myProperty, which only goes back 10 years on a house, and a buyer’s lawyer who knows walls will run both.
Between 2 neighbours the City stays out of it completely, a wall over the line is a civil matter, and the only person on the street both sides will believe is the surveyor, whose report costs $800 to $1,200 and takes 3 to 4 weeks. Sungreen’s line on who pays when the wall fails is the fairest we found, “elevation alone does not decide fault”, the blame follows whoever changed the grade or sent the water, which may be the uphill owner who raised a patio or the downhill owner who dug a basement window well, and it might be neither until a crack shows.
Their other point is the one to act on now, a wall touching or crossing the line needs the neighbour’s consent in writing, with names, both addresses, the date and what is being built, because the inspectors ask for documents, not stories. The 3 plan drawings above are the layouts where none of this applies, the retaining wall sits a metre or 2 inside the lot holding the grade, and the fence stands on the line by itself on undisturbed ground, so each one has its own owner and its own permit.
What A Calgary Wall Costs, And Whose Numbers These Are

The ladder in the chart, $120 a linear foot for a 1 foot wall rising by $120 for every foot of height, is 1 Calgary contractor’s published estimate, and it is a fair ladder, but it is not a survey and no 2 Calgary quotes we have read price the same way. Sungreen quotes by the square foot of exposed face, others quote by the running foot at a height, so a quote for retaining wall cost in Calgary will arrive in 1 of those 2 shapes and has to be converted before it can be compared with the next one. What the ladder does get right is why the price climbs faster than the wall does, each foot of height adds more gravel under it, more drain rock behind it, and above 1 metre the development permit, above 1.2 metres the engineer’s drawings and the building permit fee, which is why a 4 foot wall will cost a good deal more than twice a 2 foot one.
Natural stone would run well above the block figures and a poured wall with a stone veneer higher again, timber ties come in cheaper and rot sooner in a climate that freezes and thaws from October to April. Whatever the material, have the quote state the wall height in metres from the low side grade, the base depth, and where the drain pipe will daylight, because the height in metres from grade is the number the City will measure it by, and the other 2 are the parts of the wall that will be under the sod by the time anyone wants to check.